Radome Inflation Day Feb 19, 2008
After waiting a few weeks for a 2 day window of good weather the new Bird-Air radome is installed.
Antenna Installation Part 1, Dec 20, 2007
The pedestal has been put up on the new foundation. The sidearm-counterweight modifications are complete and the antenna has been installed on the pedestal.
Pedestal Work, Aug 16, 2007
The installation of the new dual-offset antenna was delayed several months to allow for some necessary pedestal refurbishment.
RF Instrument Lab, Aug 3, 2007
A new dedicated RF instrument laboratory room was created at the CHILL facility, sporting some of the latest test equipment from Agilent and Tektronix.
Pouring a new foundation for the pedestal and radome, July 6, 2007
The new radome required a larger setback from the site boundaries. Consequently, the site was expanded to the east, and a new foundation was prepared just to the northeast of the previous radar location.
Site Preparation, June 1, 2007
Construction begins on the foundation and infrastructure to support the new dual-offset feed antenna system for the CSU-CHILL Radar.