;[[Aug 16, 2007 Pedestal Work]]
;[[Aug 16, 2007 Pedestal Work]]
The installation of the new dual-offset antenna was delayed several months to allow for some necessary pedestal refurbishment.
:The installation of the new dual-offset antenna was delayed several months to allow for some necessary pedestal refurbishment.


;[[Aug 3, 2007 RF Instrument Lab]]
;[[Aug 3, 2007 RF Instrument Lab]]

Revision as of 15:44, 2 January 2008

Current Events

Dec 20, 2007 Antenna Installation Part 1
The pedestal has been put up on the new foundation. The sidearm-counterweight modifications are complete and the antenna has been installed on the pedestal.
Aug 16, 2007 Pedestal Work
The installation of the new dual-offset antenna was delayed several months to allow for some necessary pedestal refurbishment.
Aug 3, 2007 RF Instrument Lab
A new dedicated RF instrument laboratory room was created at the CHILL facility, sporting some of the latest test equipment from Agilent and Tektronix.
July 6, 2007 Pouring a new foundation for the pedestal and radome
The new radome required a larger setback from the site boundaries. Consequently, the site was expanded to the east, and a new foundation was prepared just to the northeast of the previous radar location.
June 1, 2007 Site Preparation
Construction begins on the foundation and infrastructure to support the new dual-offset feed antenna system for the CSU-CHILL Radar.